Extract from the table of deliverables of AIDA for the Common Software Tools work package (WP2)

2011
Del no Deliverable Name Nature Dissemination level Delivery date Actual /Forecast delivery date Status/ Not submitted Contractual Yes/No Comments
D2.1 Project web infrastructure to document software packages O PU M03 30/04/11
M03
     
D2.2 Central code repositories and other infrastructure required for the software development O PP M04 31/05/11
M04
     
D2.3 Software design for geometry toolkit including the interfaces for the reconstruction toolkits R PU M12        
D2.4 Software design for tracking toolkit R PU M12        
D2.5 Software design for PFA tools R PU M12        
2012
Del no Deliverable Name Nature Dissemination level Delivery date Actual /Forecast delivery date Status/ Not submitted Contractual Yes/No Comments
D2.6 Design for handling the pile-up in sLHC R PU M17        
2014
Del no Deliverable Name Nature Dissemination level Delivery date Actual /Forecast delivery date Status/ Not submitted Contractual Yes/No Comments
D2.7 Software toolkit for detector geometry, materials and detection technologies O PU M38        
D2.8 Software toolkit with tracking algorithms O PU M38        
D2.9 Particle Flow software tools O PU M38        
D2.10 Alignment tools software tools O PU M38        
D2.11 Trigger simulation software tool O PU M38